SOP for Discom

The Commission through Supply Code and Standard of Performance Regulations, 2021 has stipulated timelines for performing various consumer-related activities by distribution licensees and compensation to be paid to the consumer for the delay in performing such activities. SoP for some of the activities are as below:
Sr. No. Activity/Event Standard Timelines Compensation Payble
Provision of Supply
1 Connection from existing Network Metro Area – 7 days Urban Area – 15 days Rural Area – 30 days Rs 50 per week or part thereof – maximum of twice the SCC for that Category.
2 if extension or augmentation of distributing main is required Three (3) months
3 If commissioning of new sub-station forming a part of the distribution system is required One (1) year
Restoration of Supply
1 Fuse off call Urban Area – 3 Hrs Rs 50 per hour -  maximum of Rs 500 for LT Consumer Rs 100 per hour  -maximum of Rs 1000 for HT Consumer.
Rural Area – 18 Hrs
2 Overhead Line Urban Area – 4 Hrs
Rural Area – 24 Hrs
3 Under Ground / Bus Riser Urban Area – 8 Hrs
Rural Area – 48 Hrs
4 Distribution transformer and associated Switchgear failure Urban Area – 18 Hrs
Rural Area – 48 Hrs
5 Burnt Meter Urban Area – 18 Hrs
Rural Area – 48 Hrs
Meters
1 Meter inspection Urban Area – 4 Hrs Rs. 50 per week - maximum of Rs 250.
Rural Area – 12 Hrs
2 Replacement of meter if found faulty Within subsequent billing cycle
Reconnection
1 Reconnection of a Consumer - Disconnected for less than six (6) months Urban Area – 4 Hrs Rs 50 per hour – maximum of Rs 250.
Rural Area – 12 Hrs
For more details kindly refer Annexure ‘II’ of MERC (Electricity Supply Code and Standards of Performance of Distribution Licensees including Power Quality) Regulations, 2021.