Hearing
S.No. | Schedule | Description | Status | Attachments |
---|---|---|---|---|
1 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Tata Power Company-Distribution seeking declaration that delay in the
switchover of consumers by Adani Electricity Mumbai Ltd.-Distribution is illegal and contrary to the Commission’s Order dated 12 June 2017 in Case Nos. 182 of 2014 and 40 of 2015 read with the Supply Code and Standard of Performance Regulations.
82 of 2021
|
Completed | |
2 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Adani Electricity Mumbai Ltd.-Distribution seeking directions against Tata Power Company Ltd.-Distribution for willful violation of the Order dated 12 June 2017 passed by the Commission in Case Nos. 182 of 2014 and 40 of 2015, while carrying out switchover of existing consumers in Mumbai Suburban area.
135 of 2021
|
Completed | |
3 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Morries Energy Ltd. regarding non-adjustment of Open Access units for September 2021.
12 of 2023
|
Completed | |
4 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Maharashtra State Electricity Distribution Company Limited (MSEDCL) seeking directions under Section 86 (1) (f) read with 86 (1) (k) of the Electricity Act, 2003 read with Article 4, 10, 18 & 17 of the Energy Banking Agreement (EBA) dated 29 June 2022 executed between MSEDCL and SPTPL for banking of Energy.
122 of 2023
|
Completed | |
5 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Schreiber Dynamics Dairies Pvt. Ltd. for not allowing Power Factor Incentive on Open Access charges by the Respondent, thereby violated Clause No. 16.3 of Distribution Open Access Regulations-2016 issued by MERC, hence liable for action under Section 142, 146 & 149 of Electricity Act, 2003.
178 of 2023
|
Completed | |
6 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Mr. Harshad Sheth seeking for an appropriate orders and directions regarding validity of T.O. Circular No. C.E. (Dist.)/D-III/NSC/30011 dated 20 December 2018 issued by MSEDCL and subsequent modifications made thereto.
182 of 2023
|
Completed | |
7 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Ratnagiri Gas and Power Private Ltd. under Section 65 of the Electricity Act, 2003 read with Section 108 instruction from Govt of Maharashtra praying for refund of transmission charges and losses levied during the sale of power from RGPPL to Indian Railways (2017-2022).
173 of 2023
|
Withdrawn | |
8 | Tue 21/05/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Team Ferro Alloys Pvt Ltd. for getting refund from MSEDCL for differential demand charges considering 25% demand charges with interest as per order of Commission in Case No. 166 of 2020, getting interest from MSEDCL against delayed payment for energy supplied as per conditions of power purchase agreement and refund of excess security deposit held with MSEDCL.
174 of 2023
|
Completed |