Hearing
S.No. | Schedule | Description | Status | Attachments |
---|---|---|---|---|
1 | Tue 27/02/2024 11:00:00 AM |
e-Public Hearing
Hearing on Suo-Motu draft Order on Renewable Energy Tariff for FY 2024-25
3 of 2024
|
Completed | |
2 | Tue 27/02/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition filed by RattanIndia Power Limited seeking compensation on account of various change in law events.
86 of 2023
|
Rescheduled on Tuesday 20/February/2024 10:30 AM | |
3 | Tue 27/02/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Classic Marble Company Pvt. Limited (CMCPL) under Sections 86 (1) (f), 142, 146 and 149 of the Electricity Act, 2003 for Non-Compliance of the Commission’s Orders dated 7 September 2021 in Case No. 148 of 2020 by MSEDCL.
97 of 2023
|
Rescheduled on Tuesday 20/February/2024 10:30 AM | |
4 | Tue 27/02/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of MSEDCL for reclassification of wind zones of wind energy projects in Maharashtra.
And
Interlocutory application for impleadment of Wind Independent Power Producers Association as a necessary and proper party in Case No. 114 of 2023.
And
Interlocutory Application of Bothe Windfarm Development Pvt. Ltd. for challenging the maintainability of the Petition No. 114 of 2023 filed by MSEDCL and the jurisdiction of this Hon’ble Commission to entertain and grant relief sought by MSEDCL in the present Petition.
And
Interlocutory Application of Vena Energy MH Wind Power Pvt. Ltd. for challenging the maintainability of the Petition No. 114 of 2023 filed by MSEDCL as the reliefs sought by MSEDCL to the extent that it may lead to altercation/modification/amendment of the existing EPAs executed with the Applicant or the tariff fixed thereunder.
114 of 2023 & I.A. No. 61, 66, 67 of 2023 in Case No.114 of 2023
|
Rescheduled on Tuesday 20/February/2024 10:30 AM | |
5 | Tue 27/02/2024 10:30:00 AM |
e-Public Hearing
Inviting Suggestions and Objections on The Tata Power Company Limited- Distribution's Tariff Petition for Truing up of FY 2022-23, Provisional Truing up for FY 2023-24 and approval of Revised ARR and Tariff for FY 2024-25 [Case No. 237 of 2023]
237 of 2023
|
Completed | |
6 | Tue 27/02/2024 10:30:00 AM |
e-Hearing through Video Conferencing
Petition of Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) for seeking guidance and directions for further course of action to be taken for procurement of solar power under the Mukhyamantri Saur Krushi Vahini Yojana 2.0.
20 of 2024
|
Completed |