40 of 2014
S.No. | Order Date | Case No. | Order Type | Description | Attachments |
---|---|---|---|---|---|
1 | 27-03-2014 | 40 of 2014 | Works of Licensee Rules, 2012 (Right of Way)/ Line Compensation | Case No 40 of 2014 : Petition filed by Shri Ashok Pandharinath Shinde & Shri Sudam Devrao Shinde before the Commission for non-compliance by MSETCL of Sections 67, and 68 of the Electricity Act , 2003 read with Maharashtra Electricity Works of Licensees Rules, 2012, while erection of the transmission line towers on their land . The Petitioners also seeking the revision to the Order passed by the District Collector, Jalna on 24 January, 2013, and enhancement in the compensation determined by the District Collector, Jalna and action against MSETCL as per Sections 142 & 146 of the Electricity Act, 2003. |